The Rangitāiki Floodway is a multi-stage project designed to take pressure off the Rangitāiki River in a flood event, by diverting some of its flow, via a Spillway, into near-by farmland between stopbanks (known as the Floodway) and out the Rangitāiki River mouth at Thornton.

Why are we doing this?

The Bay of Plenty’s most frequent natural hazard is flooding. As we have seen throughout history, the results of a significant flood event can be catastrophic to the lives and livelihoods of those in flood-affected areas.

The Rangitāiki River has a long history of flooding. Between the 1960s and 1980s, the Rangitāiki Floodway was created by the Bay of Plenty Catchments Commission to provide flood protection to the community in and around Edgecumbe.

Over time, the level of flood protection that the Floodway offers has decreased, for reasons such as ground settlement. As technology has advanced, we can also better predict what future flood events may look like and how our flood defences need to be constructed.

In 2009, Bay of Plenty Regional Council was granted resource consent to increase the amount of water that could be diverted into the Floodway (190 cubic metres per second) and upgrade the existing Spillway to better control how the water gets into the Floodway. Upgrades to the Floodway have been ongoing since then.

By diverting the consented amount of water during a flood event, in a controlled manner, through the Floodway, we can reduce the flood levels in the Rangitāiki River upstream of Edgecumbe, reducing pressure on the river near populated areas before it can cause disruption.

stage 6b and 6c
Construction to raise the bank heights (March 2022).

Construction to upgrade the Floodway began in 2011 and will be complete in 2023. To date, there have been seven stages of the project, each stage with its own engineering considerations.

Upgrades that have been undertaken on the Floodway include:

  • Sections of the existing Floodway channel have been widened.
  • Stopbanks have been reconstructed to raise the bank heights.
  • Culverts have been upgraded to support the new stopbank design.
  • Greater seepage control beneath the ground has been installed.
  • A new bifurcation cut was made at Thornton Hall Road. This allows water from the Floodway to exit into the Rangitāiki River mouth at two places, instead of one.
  • A road bridge was created over the new Floodway exit and a wetland was established between the two exits as an ideal spot for inanga spawning.

The swing gates at McCracken and McLeans Road are the final defences to be constructed. In a flood event, the swing gates act as a barrier to close the roads and maintain the same stopbank height of the Floodway, to convey the water out to sea.

The Floodway (and Spillway) will form part of a network of protection along the Rangitāiki River. This includes the Rangitāiki Floodwalls and future work along the lower catchment. In a flood event, these defences will work together to help protect communities along the awa, by managing the increased water levels and reducing pressure on other flood defences.

Crown Infrastructure Funding

Bay of Plenty Regional Council received funding for Stage 6 of the Floodway and the Spillway from Central Government’s Crown Infrastructure Funding for this project as part of the Climate Resilience Programme ($10.275M). This funding was granted as part of the Covid-19 Response and Recovery Fund, and was one of six projects Bay of Plenty Regional Council received funding for

The purpose of the Spillway is to alleviate pressure on the Rangitāiki River during large flood events by diverting floodwater away from the main river upstream of the Edgecumbe township and into the Floodway.

When the river reaches a certain level, the Spillway allows water to pass over a section of lowered stopbank (fixed crest weir) and into an area of paddock near Hydro Road. This water is then channelled into the Floodway and out to the Rangitāiki River mouth.

The Spillway is designed based on what the predicted river level could be at the Spillway during operation and the level determines how much flow will go over the Spillway. The Rangitāiki Spillway is designed with contingency gates, which provides ‘back up’ if required flows are not met, giving reassurance that pressure can be taken off the Rangitāiki River and the flood defences down stream of Edgecumbe.

diagram

In October 2022, we publicly notified the variation to the resource consent application, for the construction and operation of the Spillway (located at 266 Hydro Road, Edgecumbe).

While consent was first granted in 2009, we reapplied for consent as the design and operation of the Spillway had changed in 2020, to have greater certainty of its operation.

The 2009 design utilised a reinforced earth stopbank (fixed crest weir) and an inflatable rubber dam (a rubber, cylinder-shaped balloon that can be inflated and deflated to control the water flow into the Floodway).

Since obtaining the 2009 consent, we determined that the consented Spillway design would not be the most suitable or reliable option (more on this below).

We went back to the community with an updated design (lower fixed crest weir with contingency gates) in 2020 and 2023, and through this process it was confirmed that this design was the preferred approach. As a result, changes to the resource consent were made to reflect the updated design.

After community consultation in 2020, a detailed design phase began.

During this phase, river modelling and ground investigations identified key risks that needed to be addressed. These risks were seepage and erodibility (sour) of these structures when the Spillway is in operation, as well as creating certainty that the Spillway achieves required flows.

Based on this, a detailed design was developed to address the above issues.

Because of these design changes (and a few other factors), the estimated cost to upgrade the Rangitāiki Spillway increased to $7.8M since consulting with the community in 2020 (the initial estimate was $2.8M).

Why has the cost increased?

  • The design option that was presented in 2020 proposed that the fixed crest weir would be finished in reinforced grass. This is now a 114m concrete capped section, with erosion protection (such as riprap) up and down stream of the weir. The concrete cap ensures the weir can handle river flows during operation and maintains its dimensions. It also needs less maintenance than reinforced grass.
  • Other design requirements, such as the need for installing sheet piles around the structures, sub-structure drainage and additional paddock contouring, are all required to manage risk during operation.
  • Since the 2020 estimate, high inflation, rising interest rates, Covid-19 and high labour costs have led to price hikes across all sectors (including construction).

The cost increase will be passed on to Rangitāiki-Tarawera ratepayers via targeted ratepayers over the next 20 years. There will also be a small increase in general rates.

Consultation was held with the community in April 2023 about the cost increase. We presented two options for feedback: Construct the Spillway design as planned, or only construct the fixed crest weir.

While the latter was a cheaper option ($3.8M), there would be no contingency ‘back up’ and the community would be without reassurance of its operation.

The majority of community consulted supported the full design option, and this was approved at Council in May 2023.

Frequently asked questions

The new, proposed Spillway design will ‘activate’ at a lower river level (a more frequent flood event).

However, the volume of water sitting in the Floodway during a smaller event will be less – for example, there may be localised ponding or increased water levels in Reid Central Canal only (amount of water subject to size of flood event).

Through the detail design process, a lot of effort has gone into setting the fixed crest weir at an optimal level, based on predicted river levels, to ensure the Spillway’s operation during a flood event.

Unfortunately, there will always be some uncertainties which cannot be eliminated, i.e. there will always be an element of uncertainty as to how the Rangitāiki River will ‘behave’ during a flood event.

As an example, if the river level was 100mm lower than predicted, this could account for an approximate 9% flow reduction. While this may not seem like much, it would be a significant in a flood event and highlights the importance of having contingency ‘back up’.

This is why having the contingency gates provides ‘back up’, by allowing controlled flow into the Floodway. 

Prior to reaching Te Teko, the Rangitāiki River passes through Lake Aniwaniwa, then into Matahina Dam. Both used for hydroelectric power generation.

For Matahina Dam, the role of dam management is to lower the lake level before a flood peak so that, at peak flows, the outflow from the dam can be kept significantly lower than the inflow for as long as possible that is consistent with the safety of the dam.

Stage 6b and 6c
Stage 6b and 6c

Project Updates

30 days ago

Council approves construction of proposed Rangitāiki Spillway design

Bay of Plenty Regional Council Councillors have approved increase in budget for the construction of the Rangitāiki Spillway, following overwhelming support from the community.

In an event, the Spillway enables water from the Rangitāiki River to pass over a fixed crest weir (lowered, concrete-covered stopbank) and into the Floodway. This will help divert water away from the Rangitāiki River and reduce the risk of significant flood damage to both rural and urban areas.

Read more.

3 months ago

Community session to be held in Edgecumbe to discuss the Rangitāiki Spillway

Bay of Plenty Regional Council is holding a community session in Edgecumbe to discuss the Rangitāiki Spillway project.

Community session to be held in Edgecumbe to discuss the Rangitāiki Spillway

Bay of Plenty Regional Council is holding a community session in Edgecumbe to discuss the Rangitāiki Spillway project.

The Spillway needs to be upgraded as it is part of the Rangitāiki Floodway, a key piece of flood defence infrastructure to help protect the community in a flood event.

In an event, the Floodway and Spillway upgrades will help divert water away from the Rangitāiki River. This helps reduce the risk of significant flood damage to both rural and urban areas (for example, the economic damage of the 2017 event was estimated to be $95M).

Engineering Manager Mark Townsend says since Regional Council last consulted with the community on the project in 2020, the estimated cost to upgrade the Spillway has increased.

The purpose of the community session is to have a conversation about why that is, how it will affect ratepayers and what the options are in a challenging economic climate.

“High inflation, rising interest rates, Covid-19 and high labour costs have led to price hikes across all sector, including construction.”

He adds that during the detail design phase of the project, river modelling and ground investigations identified key risks that needed to be addressed.

“These risks were seepage and erodibility (scour) of the structures when the Spillway is in operation, as well as a need to create certainty that the Spillway would achieve the required flows into the Floodway.

“Since meeting with the community in 2020, the Spillway has been designed to address these issues, better manage water flows over the Spillway and give the community reassurance that it will perform as required. These design changes include additional concrete work, sheet piling around the structure for seepage control, drainage and paddock contouring.”

The current estimate to construct the revised design in its entirety is $7.8M (less $2.1M of central government funding), a $5M increase from the original estimate ($2.8M). The increased costs will be passed on to ratepayers via targeted rates.

The community session is being held on Saturday 15 April from 10.30am to 12.30pm at the Edgecumbe War Memorial Hall (corner of Kauri Street and Main Street), Edgecumbe.

If you wish to attend, please RSVP (for catering purposes) to engineering@boprc.govt.nz

6 months ago

Construction update: Disruption on McCracken and McLean Roads

Bay of Plenty Regional Council will begin construction for the final stage of the Rangitāiki Floodway from Monday 1 May 2023.

The Rangitāiki Floodway is a key piece of flood defence infrastructure to help protect the lives and livelihoods of the community.

Construction update: Disruption on McCracken and McLean Roads

Bay of Plenty Regional Council will begin construction for the final stage of the Rangitāiki Floodway from Monday 1 May 2023.

The Rangitāiki Floodway is a key piece of flood defence infrastructure to help protect the lives and livelihoods of the community.

In a flood event, the Rangitāiki Floodway is designed to take pressure off the Rangitāiki River by diverting some of its flow (via a Spillway) into near-by farmland between stopbanks and out the Rangitāiki River mouth at Thornton.

diagram of swingate

What’s happening?

The construction process involves installing swing gates (heavy duty steel flood barriers) at two sites along the Rangitāiki Floodway:

  • Site one: Two sets on McCracken Road (located between Hydro Road and Western Drain Road, Edgecumbe)
    map

  • Site two: Two sets on McLean Road (located between East Bank Road and Western Drain Road, Edgecumbe).
    map

When the Floodway is activated, these swing gates will have two functions: They will act as a barrier on the road, keeping the community from entering a flood zone, and maintain the stopbank height of the Floodway, creating a channel that helps send water out to the Rangitāiki River mouth.

When not in use, the gates are locked open, allowing uninterrupted traffic flow.

How might this impact you?

Construction is due to begin from Monday 1 May 2023 and each site is expected to take approximately seven weeks.

During construction, road closures will be in place around the swing gate site and there will be no through traffic. Residents will be able to access their homes, however detours will be in place to travel to and from McLean and McCracken Roads.

We will keep you updated on construction and road closures via this project page.

If you have any questions or concerns, please contact Project Lead Niroy Sumeran on engineering@boprc.govt.nz or 0800 884 880.

Thank you for your patience during this time.

9 months ago

Regional Council applies for variation to Spillway consent

Bay of Plenty Regional Council have made the commitment to publicly notify the variation to the resource consent application, for the construction and operation of the Spillway (located at 266 Hydro Road, Edgecumbe).

While consent was first granted in 2009, we are reapplying for consent as the design of the Spillway has changed to enable greater certainty of its operation in a flood event.  

Regional Council applies for variation to Spillway consent

Bay of Plenty Regional Council have made the commitment to publicly notify the variation to the resource consent application, for the construction and operation of the Spillway (located at 266 Hydro Road, Edgecumbe).

While consent was first granted in 2009, we are reapplying for consent as the design of the Spillway has changed to enable greater certainty of its operation in a flood event.  

The original Spillway design was utilising a reinforced earth stopbank (fixed crest weir) and an inflatable rubber dam (a rubber, cylinder-shaped balloon that can be inflated and deflated to control the water flow into the Spillway).

Since obtaining that original consent, we have determined that the consented Spillway design would not be the most suitable or reliable option.

There are a few reasons why we are publicly notifying the community about our reapplication:

  • The Spillway design has changed. This new application is seeking approval to change the current approved Spillway design to a lower fixed crest weir structure (a lower level stopbank capped with concrete). We are also adding three contingency gates as back-up.
  • In the new proposed design, the Spillway will ‘activate’ at a lower river flow threshold, meaning that water may run into the Spillway and Floodway more frequently. This provides greater certainty around operation in a flood event.
  • Significant earthworks are required to create the new Spillway design and paddock contouring downstream of the Spillway is required to channel water into the Floodway.
  • We have made a commitment to keep the community informed with progress to this project as it is of public interest and a key piece of infrastructure to help protect the community.

Access the full consent document and make a submission.

about 2 years ago

End of year floodwall project wrap

We’re two thirds of the way through the floodwall replacements with the Greig Road and East Bank Road walls now complete.

Watch this video to see all the progress we’ve made this year:

about 2 years ago

Work recommencing on Rangitāiki Floodway

We are recommencing work on the Rangitāiki Floodway project on the outskirts of Edgecumbe in the section located between SH2 and Mclean’s Road.

Please take extra care on the roads around the site, we’ll be taking extra care too.

We're doing this work to improve how water travels down the floodway which will reduce the pressure on the Rangitāiki River stopbanks during large flood events.

about 2 years ago

Construction of Stage 6c underway

Construction of Stage 6c of the Rangitāiki Floodway is underway after resource consent was granted.

This stage will see 3km of the right stopbank raised and has been split into two sections.

Construction of Stage 6c underway

Construction of Stage 6c of the Rangitāiki Floodway is underway after resource consent was granted.

This stage will see 3km of the right stopbank raised and has been split into two sections.

For the initial section, stockpiled construction earthfill will be transported from our storage site at the State Highway 2 end to halfway down the stopbank for construction. Contractors will then work back towards State Highway 2.

There is a temporary speed restriction of 50km/h (as identified on the map above) on State Highway 2 as trucks will be turning onto site.

We are hoping to complete to this section before July 2021, weather permitting.

We will then have to stop the project over winter, and will begin raising the second half of the right stopbank later in the year.

We’re doing this work to improve how water travels down the Rangitāiki Floodway (Reids Central Canal), which will in turn reduce the pressure on the Rangitāiki River stopbanks during large flood events.

Detailed modelling is continuing to feed into the final design of the spillway.

map of earth works ad speed restriction
about 3 years ago

Rangitāiki Floodway Project update

The summer construction season is in full swing with steady progress being made on raising the stopbanks as part of the Rangitāiki Floodway Project.

Earthworks for Stage 6a involved raising the left stopbank of the floodway north of McLean Road. Fencing and grass reinstatement will see this stage completed by the end of March.

Rangitāiki Floodway Project update

The summer construction season is in full swing with steady progress being made on raising the stopbanks as part of the Rangitāiki Floodway Project.

Earthworks for Stage 6a involved raising the left stopbank of the floodway north of McLean Road. Fencing and grass reinstatement will see this stage completed by the end of March.

Work continues on Stage 6b with the raising of the left stopbank from McLean Road to State Highway 2. This stage has a likely completion timeframe of May/June.

Preparation works on the opposite right stopbank (6c) started in early February, while the earthworks resource consent for this stage is still pending.

Two thirds of the work on raising the stopbank for Stage 7 (between Hydro Road and SH2) was completed last year with the final section to be finished by June.

Our contractors’ trucks and trailers will be transporting material from Awakeri quarries to the various work areas during this period. 

Meanwhile, detailed modelling is continuing to feed into the final design of the spillway.

Rangitāiki Floodway Project
about 3 years ago

Funding received from Central Government’s Crown Infrastructure Funding

Bay of Plenty Regional Council has received funding from Central Government’s Crown Infrastructure Funding for the Rangitāiki Floodway and Spillway.

Toi Moana put the project up as a shovel ready project after Central Government announced it wanted to help with economic recovery after Covid 19.

The funding covers 75% of:

  • Stage 6 of the Floodway - $10.915 million
  • The Spillway - $2.8 million

This was one of six projects Bay of Plenty Regional council received funding for. Find out about the other projects.

about 4 years ago

Further consultation this Saturday

Thank you to those who were able to take part in the recent online consultation about the next stages of the Rangitāiki Floodway Project.

Further consultation this Saturday

Thank you to those who were able to take part in the recent online consultation about the next stages of the Rangitāiki Floodway Project.

Now that COVID-19 alert levels have eased, Council is inviting anyone with an interest in the Rangitāiki Floodway to another opportunity to learn more, and tell us what you think, about Stage 6 and the preferred spillway design.

Some aspects of the these stages have changed, so this consultation will explain the reasons; the relating cost increases and the potential rating impacts.

If you live within the Rangitāiki-Tarawera catchment, it’s important to find out more, and have your say.

Rangitāiki Cosmopolitan Club, 9 Bridge St, Edgecumbe

13 June 2020 - 10.00am

about 4 years ago

Rangitāiki Floodway Stage 6 update

Previously a ponding option downstream of Fonterra was being looked at to reduce the overall project costs. This option has now been abandoned.

This is because detailed design showed that this option was in fact going to be a more expensive option and the benefits were not as great as originally assessed.

Rangitāiki Floodway Stage 6 update

Previously a ponding option downstream of Fonterra was being looked at to reduce the overall project costs. This option has now been abandoned.

This is because detailed design showed that this option was in fact going to be a more expensive option and the benefits were not as great as originally assessed.

Consequently the stopbank raising option is now the preferred option. The detailed design also showed that for all options the scale of work required had been under represented in previous modelling results.

Due to the above, Stage 7 of the Rangitāiki Floodway was brought forward to be completed before Stage 6.

The reason for this is that Stage 6 is a far more complex stage and more time was needed to complete the detailed design and geotechnical testing to inform the final design.

The final estimate for Stage 6 has now been produced and is shown in table 1 below:

Stage

LTP Cost Estimate (000)

Updated Estimate (000)

Difference (000)

6

$ 2,428

$ 10,915

$8,497

Rangitāiki Floodway Spillway

During 2018 consultation was undertaken within the local community on options for the spillway design. The proposed option was for a lower fixed crest weir with contingency radial gates and was generally supported at the culmination of the consultation on 24th November 2018.

The option that had been prepared prior to this consultation taking place in the Long Term Plan (LTP) was for a lower fixed crest weir with no contingency allowance.

Table 2 below shows the increase in cost for the Spillway.

Stage

LTP Cost Estimate – Lower Fixed Crest Weir (000)

Lower Fixed Crest Weir with contingency gates (000)

Spillway

$ 0.360

$ 2,800


Crown Infrastructure Partners (CIP) funding

Central Government announced that it wants to help with economic recovery once we are out of the Covid 19 restrictions. We have put the Rangitāiki Floodway project up as a “spade ready” project that Central Government could help fund. If successful, the increased costs outlined above could be off-set by the CIP funding. 

Key links:

about 4 years ago

Stage 7 of the Rangitāiki Floodway Upgrade Project

We’re about to begin Stage 7 of the Rangitāiki Floodway Upgrade Project – the section from Hydro Road to State Highway 2.

Stage 7 of the Rangitaiki Floodway Upgrade Project

We’re about to begin Stage 7 of the Rangitāiki Floodway Upgrade Project – the section from Hydro Road to State Highway 2.

We’re doing this work to improve how water travels down the Rangitāiki Floodway (Reids Central Canal), which will in turn reduce the pressure on the Rangitāiki River stopbanks during large flood events. Construction works will begin in January 2020 and are expected to be completed in June 2020 but are weather dependant. We’ll keep you informed if these dates change or work goes longer than expected.

If you have further questions, please call 0800 884 880 to speak to a staff member about the project.

Stage 7 map Rangitaiki Floodway Upgrade
about 4 years ago

New bridge at Thornton

Stage 5 of the Rangitāiki Floodway Project has reached a significant milestone with bridge construction nearing completion on Thornton Hall Road near Whakatāne.

New bridge at Thornton

Stage 5 of the Rangitāiki Floodway Project has reached a significant milestone with bridge construction nearing completion on Thornton Hall Road near Whakatāne.

The Rangitāiki Floodway Project is being built in stages to take pressure off the flood-prone Rangitāiki River. The current work, which started in late February this year, has seen the construction of a bifurcation channel and the upgrading of Thornton Hall Road, including the new bridge.

Project Manager for Stage 5, Bay of Plenty Regional Council’s Civil Construction Engineer, Jordan Mandery says local residents will see a few final works in the area before the current stage is complete.

“Getting the bridge in place is a significant milestone. We have the bridge beams on, so now we can complete the abutments and bridge approach. We expect the subbase layers of the road construction to get underway shortly and be completed by the end of October. At that point we can divert traffic across the bridge and remove the final piece of land and open the bifurcation channel,” Mr Mandery explains.

Activity around Thornton Hall Road has bound together several other improvements including upgrading the powerlines in conjunction with Horizon Energy and working with Whakatāne District Council to widen the road.

At the same time, a wetland has been created in the area where Reid’s Central Canal will meet the Rangitaiki River. Regional Council’s Land Management team has overseen initial plantings, with more scheduled once the bifurcation is open.

“I’d like to thank the residents and motorists for their cooperation and patience while these critical works are undertaken. Please continue to be considerate and follow the direction of the temporary traffic management while driving past the site as it is important for the safety of our contractors.”

“We are also looking to raise the section of stopbank alongside Thornton Road which is set out in our Long Term Plan, but we’ve decided to bring that forward while we are working in the area, so people will see that work taking place in coming weeks,” Mr Mandery said.

about 5 years ago

Floodway construction progress

Check out this short video of a recent drone flight over the completed Stage 4 works and the Stage 5 works currently in progress. 

 

Floodway construction progress

Check out this short video of a recent drone flight over the completed Stage 4 works and the Stage 5 works currently in progress.

Stage 5 involves creating a bifurcation cut to connect the Rangitāiki Floodway with the Rangitāiki River, as well as building a bridge over the new bifurcation and undertaking stopbank overlay works along Thornton Hall Road. A wetland is also being created to help encourage wildlife into the area. These works are expected to be completed in September 2019 and we hope you will share the journey with us as we post regular updates of the works progress.

Rangitāiki Floodway drone shot
about 5 years ago

Drone survey taking place next week

The Bay of Plenty Regional Council will be undertaking a drone survey of sections of the Rangitāiki Floodway during the week of 13 – 17 May to provide council engineers with a Digital Elevation Model (DEM) which will feed into the design for Stage 7 of the Floodway Project.

Drone survey taking place next week

The Bay of Plenty Regional Council will be undertaking a drone survey of sections of the Rangitāiki Floodway during the week of 13 – 17 May to provide council engineers with a Digital Elevation Model (DEM) which will feed into the design for Stage 7 of the Floodway Project.

The data being collected is high resolution aerial photography used for photogrammetric modelling purposes and will be used for internal purposes only. The survey will be carried out by Regional Council engineers who will be wearing Hi-Vis clothing and will be in a branded Bay of Plenty Regional Council vehicle. Please feel free to approach them on the day should you have any questions.

 

Rangitāiki floodway project stage 4
about 5 years ago

Bridge and bifurcation works get on the road

Initial site preparation works started on Monday 25 February on the Reid’s Canal bifurcation which is Stage 5 of the multi-stage Rangitāiki Floodway Upgrade Project commenced in 2011.

Bridge and bifurcation works get on the road

Initial site preparation works started on Monday 25 February on the Reid’s Canal bifurcation which is Stage 5 of the multi-stage Rangitāiki Floodway Upgrade Project commenced in 2011.

The purpose of this stage is to create a bifurcation cut from the left bank of Reid’s Central Canal across Thornton Hall Road to provide a second outlet into the Rangitaiki River and out through the river mouth. These works, which are expected to be completed within six months, also include road alignment works and a new bridge to carry Thornton Hall Road over the new canal outlet.

 Stage 5 - Tracks excavator - site establishment
about 5 years ago

Karakia held in preparation for Stage 5

Following selection of the successful tenderer for the Rangitāiki Floodway Stage 5 works, a karakia ceremony was held at the Reid’s Canal bifurcation with the Rangitāiki River on Monday 18 February, 2019.

Karakia held in preparation for Stage 5

Following selection of the successful tenderer for the Rangitāiki Floodway Stage 5 works, a karakia ceremony was held at the Reid’s Canal bifurcation with the Rangitāiki River on Monday 18 February with representatives of Ngāi Taiwhakaea, the works contractor, the project’s archaeology advisor and the Bay of Plenty Regional Council in attendance.  

Rangitaiki Floodway Upgrade Project Stage 5 - Bifurcation cut
about 5 years ago

Spillway recommendation presented at Edgecumbe information session

Around 40 interested community members, representing a number of stakeholder groups, turned out on Saturday to hear an update on the consultation process for the upgrade of the Rangitāiki Spillway.

 

Spillway recommendation presented at Edgecumbe information session

Around 40 interested community members, representing a number of stakeholder groups, turned out on Saturday to hear an update on the consultation process for the upgrade of the Rangitāiki Spillway.

The spillway – the mechanism to divert floodwater from the river into the Floodway - is planned for upgrade in 2020/21 and in recent months Council’s engineering team has been engaging with directly affected landowners and the wider community around the options for the spillway design.

Spillway presentation Edgecumbe
about 5 years ago

Rangitāiki Floodway information session

Thank you to those people who have been involved in finding out about the options for the design of the Rangitāiki Floodway spillway and potential ponding areas.

Rangitāiki Floodway information session

Thank you to those people who have been involved in finding out about the options for the design of the Rangitāiki Floodway spillway and potential ponding areas.

On Saturday, 24 November, starting at 10am there will be a further information session at the Rangitāiki Cosmopolitan Club to inform interested parties about the preferred option that will be put to Council in December.

We will be asking those attending to give an indication of their level of support for the proposed option.

For further information, please email engineering@boprc.govt.nz

Rangitāiki floodway map
about 5 years ago

Rangitāiki Floodway Stage 4 recommences

Drier spring weather has allowed the work to start again on Stage 4 of the Rangitāiki Floodway Upgrade Project after it was put on hold over winter.

Rangitāiki Floodway Stage 4 recommences

Drier spring weather has allowed the work to start again on Stage 4 of the Rangitāiki Floodway Upgrade Project after it was put on hold over winter.

Meanwhile, consultation with affected landowners and the wider community over the design options to upgrade the spillway section of the Floodway is in its final stages before a recommendation is made to Council on the preferred option (lower fixed crest weir or inflatable rubber dam). The spillway is the structure that diverts floodwater from the Rangitāiki River into the floodway and its construction and associated stopbank widening will be the final stage of the project. Keep an eye on this page for publication of an information session planned for mid-November 2018.

Rangitāiki Floodway digger
about 5 years ago

Rangitāiki Spillway site visit held in August 2018

As part of the consultation underway on the Rangitāiki Spillway, a site visit was held in Edgecumbe on 11 August this year, with over 30 people attending, including residents of property adjoining the floodway and interested members of the community.

Rangitāiki Spillway site visit held in August 2018

As part of the consultation underway on the Rangitāiki Spillway, a site visit was held in Edgecumbe on 11 August this year, with over 30 people attending, including residents of property adjoining the floodway and interested members of the community.

Those who came along on the bus trip out to the spillway off Hydro Road appreciated the chance to see the current spillway up close and hear about the options available. Once the preferred option is confirmed by Regional Council, it will go through a consent process. Construction is anticipated to start in 2020. The spillway construction will mark the final stage in this multi-stage project.

Rangitāiki Spillway site visit

Send us your questions.

Note: Fields marked * must be filled in.

Only up to 5MB allowed
Events

There are no events scheduled for this project.